|




| |
Technical Paper on the KL LRT2 System

Introduction
The Project was
awarded to PUTRA (the Operator & Client) by the Malaysian Government in 1994 for
a Design, Build and Operate contract based on a 60 year Concession Agreement.
The system is currently the longest automated driverless railway in the world,
consisting of 29km of railway, 24 stations and a depot. The trains and system
are procured from Bombardier of Canada who installed a similar system for the
Vancouver Skytrain. The project was fast-track construction and became
operational only 3½ years after first construction contract award with Section 1
opening on September 1, 1998. The second phase opened in June 1999 to complete
the Project. This timescale is recognised to be a major achievement for a modern
LRT project.
Project Structure
The structure of the Project
centres around the Operator – PUTRA, who are part of the Renong Group and are
responsible to the Ministry of Transport by it’s Concession Agreement. The MOT’s
Director General of Railways is a regulatory body with powers to stop operations
or construction work affecting the safety of the railway. The DGR took an active
role in overseeing the installation work and the final operational certification
process.
PUTRA appointed a
Project Manager for implementation, another Renong company PLRT who in turn
engaged Bechtel for international management expertise. The Consulting Engineer
was HSSI-Halcrow-DeLeuw Cather, appointed by PUTRA to advise on all technical
aspects of the Project, oversee the Systems Works, supervise the construction
works and take responsibility for the design of facilities work.
The majority of
Civil works were tendered on the engineer’s design and awarded to the Renong
construction group UEC and it’s partners. These companies constructed the
elevated guideway, depot facility, 18 elevated stations, 2 underground stations
and all power substations.
Design Build
Civil contracts were awarded for the tunneling work – to Hyundai and Hazama, 3
underground stations – SNC JV and City Properties, and also the integrated KL
Sentral station – to KLSSB.
For the Systems
works, bids were received from Canada, France, Germany and Japan, but were
eventually split and awarded to Bombardier / SNC Lavelin for the Rolling stock,
trackwork and depot equipment, to the Renong company EDSB for power supply, and
to Thorn Transit (now Cubic Transportation) for the fare collection system.
Alignment
For all
transportation projects, the alignment is the critical first stage of design and
many factors contribute to establishing the route, - such as land availability,
projected ridership from areas passed through, potential commercial development
and obstructions or restrictions from roads, rivers, railways and major
utilities. The LRT 2 alignment was established over 3 distinct sections. Section
1 commences at the Subang depot facility close to the old international airport.
The route passes through the satellite city of Petaling Jaya before entering
Kuala Lumpur city and consists of over 14km fully elevated guideway with 11
elevated stations. As mentioned earlier, this section was opened to the public
in September 1998. One station on this section is still under construction, this
being the large integrated railway station at KL Sentral that will not be
completed until January 2001.
LRT Transit Integration
Map LRT Underground Section
The 2nd
section of alignment is underground through what they call KL’s golden triangle
district which is prime commercial area. The route follows the course of River
Klang and consists of 4.4km of twin bored tunnels, cut and cover tunnels,
entrance and exit portals, 2 tunnel intervention shafts and 5 underground
stations. These stations are located strategically at the link to Star LRT and
courthouse area at Masjid Jamek, hotel and commercial area at Sultan Ismail,
historical residential area of Kampong Baru, opposite the now famous Twin Towers
at KLCC and at Ampang Park shopping and hotel area. This section opened to the
public on 1st June 1999.
The 3rd
section of alignment turns north, mostly thru Malay residential areas from Damai
to Gombak and consists of 8.2km elevated guideway, 2.3km at-grade track, 7
elevated and one sub-grade station. This section also opened in June 1999 to
complete the Project.
Ridership
To give you a
general idea of the passenger capacity of the system, the initial set-up is to
operate 35 No 2-car train sets that can accommodate around 150,000 passengers
per day, operating from 6am to midnight. This can be expanded to the design
capacity of 400,000 passengers by introducing more trains for four-car sets that
can run on the guideway at a minimum 90 second headway. The 14km journey on
Section 1 takes about 20 minutes and the full 29km journey takes 45 minutes. The
trip through the underground section only takes about 5 minutes compared to
about half an hour in normal traffic.
Transport Integration
Revenue and
passenger generation depends a lot on integration with other transportation
systems. LRT2 connects to the Star LRT which was already operational, it
connects with several bus terminals, all stations have public bus drop-offs, and
car & taxi drop off parking is provided at all station entrances. PUTRA also
operate their own feeder bus fleet of 60 buses to take passengers in local
districts to the nearest station. There are three major Park & Ride stations on
route, one at each end station and one near a main highway routing, to attract
car owners from taking their car into the city centre.
One of the prime
revenue and passenger generators for LRT2 will be the link to KTM commuter
railway services and the Express Rail Link to the new International airport from
the integrated railway station at KL Sentral. However, as the ERL will only open
in 2002, this is unlikely to produce the intended forecast for several years to
come.
Depot
The first stage
in any successful LRT is to ensure that there is a Depot facility constructed as
soon as possible to enable trains to be fully tested and operational staff
trained up before revenue service begins. This was done by constructing an
integrated modern Depot Facility on a 33Ha site within 33 months.
Elevated Stations
The focal point
of the LRT is the passenger stations and on LRT2 there are several designs. The
elevated stations have either a side platform or an island (centre) platform
type defining the layout - the selection of which type is adopted depends on the
initial alignment, land availability, projected ridership and site constraints.
For instance where track cross-overs or pocket tracks are located near a station
for operational reasons, this tends to favour island platforms.
All have the
passenger concourse below the platform, concourse being either above road level
or at-grade. The side platform stations have the guideway running straight thru
the centre, split by platforms either side and are much wider than island
platforms. The guideway is split either side of an island platform station.
Station lengths are defined by the platform length which is set for the future
4-car train length of 68m. Platform floors are flush with the train floor and
the platforms are always straight to avoid gaps at the platform edge - these
features are to provide unhindered access to the train for disabled persons.
The stations are
designed to International recognised transit standards, such as NFPA 130, the
local Malaysian Building Codes and British design codes. The structures are
reinforced concrete frames with steel roof trusses and are independant from the
viaduct structure that was erected prior to the station structure being formed.
Equipment rooms
necessary to operate the station are located at Concourse level away from the
public area. The elevated stations are naturally ventilated being open ended and
open sided with rain-screen protection for the tropical storms that occur in
Malaysia.
Underground Stations
The majority of
stations are elevated, however as mentioned earlier, there are 5 underground
stations in the centre of KL. All are centre platform types as the twin
underground tunnels are a minimum horizontal distance apart and are naturally
split either side of the platform as they connect to the station. These stations
were generally in confined city centre sites, close to the Klang river and most
had problems with existing underground utilities. The requirement for straight
level platforms at the station area also provided a challenge for the alignment
engineers to work within very tight tolerances and clear all underground
obstructions such as the river walls and piling for adjacent buildings.
The structures
are essentially a buried concrete box some 20m wide, 90 to 120m long with base
level around 20m below surface. The platform level is about 16m below ground
with the concourse level some 5m above this, leaving a rise of around 10 to 12m
from concourse to ground entrances, this of course being serviced by some of the
longest escalators installed in Malaysia. Flood control was a major issue with
the stations designed to prevent ingress from a 1 in 200 year flood level
topping the banks of the adjacent Klang river.
Design features
of the underground stations include the use of platform screen doors that allow
full air-conditioning and a complex environmental control system linked to
tunnel ventilation and fire / smoke control systems for normal and emergency
evacuation conditions. Design is based on the same International, Local and
British Codes as the elevated stations but design life for the underground
section is 120 years.
The construction
of the underground stations involved top-down excavation in all cases with
perimeter diaphragm or secant pile walls being installed prior to excavation. On
4 of the 5 stations the Contractor cut down to roof slab level, cast the roof
slab against the exposed ground with a lined surface, and used this as
protection to excavate down to concourse slab, casting this level and continuing
excavation to base slab, all the while removing spoil through strategically
spaced openings in the slabs. These slabs provided the horizontal strutting
action to restrain the perimeter walls with Masjid Jamek station requiring
additional temporary steel struts due to the close proximity of adjacent
multi-storey building foundations. At Dang Wangi station, the Contractor chose
to excavate fully down to base slab from surface, utilising temporary horizontal
struts and building upwards from base by use of a proprietary falsework system.
Viaduct Construction
That is the
passenger stations covered. In order to get these passengers from point to point
thru the city, the trainway has to be constructed. On LRT2 this consists mainly
of 22.3km elevated viaduct, 4.4km of tunnels and 2.3km of at-grade trackway. The
viaduct is constructed from single cell …. - see slide.
The box girder
precast sections were built in a covered casting yard specially set up for the
project and each segment was match cast against each other. - see slide.
The LRT guideway
construction used elevated launching gantries to install and connect the precast
segments into beam elements between pier supports. These gantries were somewhat
special in that they could articulate around tight radius curves to a minimum
100m radius. Two types were used, these being a CD type for normal spans of
between 18 to 36m and the SP type for special continuous structures over major
roads or railways for spans upto 63m.
Tunnel
The LRT2 has
also broken new ground in Kuala Lumpur by constructing the first underground
tunnels.
The ground that
the tunnels went thru consisted of alluvium, limestone and volcanic rock
intrusions. Apart from the bored tunnels, there were two sections of cut and
cover tunnel with the 500m section at Pasar Seni being of particular interest as
it rotated about itself, one over the other, due to the tight constraint of
buildings and the adjacent river. The west-end had a 180m cut & cover section
which was constructed to initiate the tunnel drive.
Settlement
monitoring was of prime concern at Masjid Jamek station where adjacent tall bank
buildings were founded on rail section piles. This however, proved to be useful
to the Contractor to assess the benefits of strut placement & removal. No
special building protection measures were needed.
This slide shows
the operation of an Earth Pressure Balance tunneling machine - the head digging
at front, spoil removed by conveyor to the rear and taken away by small
locomotive to the access shaft where it was disposed of.
All tunnel jobs
will have some problems during construction and fortunately, the LRT2 tunnels
only had minor ones with no major face losses or collapses. In fact at no point
did the ground surface above the tunnel exceed the predicted settlement
allowance of 80mm. The tunnel horizon was between 15 to 20m below ground.
Trackwork
One of the more
important features for construction was laying the steel trackway. This was
important because if it not installed correctly to stringent tolerance,
consequences may include problems with rail noise, braking and shuddering of the
train and higher wear on the wheels and rails. This installation requires to be
done by a specialist Contractor, in the case of LRT2 this was also the track
designer. The track has 2 power rails for third and fourth rail 750V traction
power operation.
|